UPSC CSE 2021 CSAT · Question 50
UPSC CSE 2021 CSAT question on Time Work Completes Job
CSAT is a qualifying paper.
- ExamUPSC CSE - CSAT
- Year2021
- PaperCSAT (General Studies Paper II)
- SubjectBasic numeracy
- TopicTime and work
- DifficultyMedium
A man completes 7/8 of a job in 21 days. How many more days will it take him to finish the job if quantum of work is further increased by 50%
Show answer
Answer: D. 15
Solution
- 7⁄8 of the job takes 21 days, so 1⁄8 takes 3 days and the full job takes 24 days.
- The work is increased by 50%, so the total work = 1.5 jobs = 12⁄8.
- Work done = 7⁄8; remaining = 12⁄8 − 7⁄8 = 5⁄8.
- Time for 5⁄8 = 5 × 3 = 15 days.
- Check: 21 + 15 = 36 days = 1.5 × 24. ✓
Why the other options are wrong
- (a) 24: the time for one whole job, not the remaining work.
- (b) 21: the time already spent on 7⁄8 of the job.
- (c) 18: 6⁄8 of the job, which assumes 1⁄8 more than is left.
Quick trick
- Count in eighths at 3 days each: total 12 eighths, 7 done, 5 left → 15 days.
Remember
Convert work to equal units, find the time per unit, then multiply by the units left.
Hence the answer is (d).
Share
Ask Atlas (5) for similar questions
- Time Work Data Inadequate — Same work-and-workers pattern, scaling men and women to find days needed.
- Time Work Complete Together — Same concept: work expressed as percentages and days, combined work for a target fraction.
- Time Work Complete Certain — Same fractional-work idea: partial work done by several workers over days, remaining work finished.
- Time Work Certain Complete — Same work-rate idea: change in amount of work or workers to change completion time.
- Time Work Monday Tuesday — Same work-rate basis: days for individual workers to complete a whole job.
← Full UPSC CSE 2021 CSAT paper · All Basic numeracy questions