A person x can complete 20% of work in 8 days and another person Y can complete 25% of the same work in 6 days. If they work together, in how many days will 40% of the work by completed?
Show answer
Answer: A. 6
Solution
- X does 20% (that is 1⁄5) in 8 days, so X alone needs 8 × 5 = 40 days for the full work.
- Y does 25% (that is 1⁄4) in 6 days, so Y alone needs 6 × 4 = 24 days.
- One-day work together = 1⁄40 + 1⁄24 = 3⁄120 + 5⁄120 = 8⁄120 = 1⁄15.
- So together they finish the whole work in 15 days.
- 40% of the work = 0.4 × 15 = 6 days.
- Check: in 6 days X does 6⁄40 = 15% and Y does 6⁄24 = 25%; 15% + 25% = 40%. ✓
Why the other options are wrong
- (b) 8: in 8 days they finish 8⁄15 ≈ 53%, more than 40%.
- (c) 10: in 10 days they finish 10⁄15 ≈ 67%.
- (d) 12: in 12 days they finish 12⁄15 = 80%.
Quick trick
- Work in percent per day: X = 20⁄8 = 2.5% a day, Y = 25⁄6 ≈ 4.17% a day, total ≈ 6.67% a day; 40 ÷ 6.67 = 6 days.
Remember
Convert each person's partial work into a full-work time, add the one-day rates, then scale to the fraction asked.
Hence the answer is (a).
Share
Ask Atlas (5) for similar questions
- Time Work Complete Certain — Same work-rate idea: partial work by individuals converted into combined daily rates.
- Time Work Data Inadequate — Same pattern of combined men and women work rates to find completion days.
- Time Work Monday Tuesday — Same basis: individual completion times combined into daily fractions of the whole work.
- Time Work Complete Piece — Individual work times combined to find overall completion time for a team.
- Time Work Completes Job — Same percent-of-job framing with work quantity and time relationships.
← Full UPSC CSE 2020 CSAT paper · All Basic numeracy questions