UPSC CSE 2022 CSAT · Question 57

UPSC CSE 2022 CSAT question on Time Work Data Inadequate

CSAT is a qualifying paper.

24 men and 12 women can do a piece of work in 30 days. In how many days can 12 men and 24. women do the same piece of work?

  1. 30 days
  2. more than 30 days
  3. Less than 30 days or more than 30 days
  4. Data is inadequate to draw any conclusion
Show answer

Answer: D. Data is inadequate to draw any conclusion

Solution

  1. The second group swaps 12 men for 12 women compared with the first group.
  2. If a man works faster than a woman, the second group is slower and needs more than 30 days; if a woman works faster, it needs fewer; if they are equal, exactly 30 days.
  3. The question does not compare a man's work with a woman's, so the answer cannot be fixed.

Why the other options are wrong

  • (a) 30 days: true only if men and women work equally fast, which is not given.
  • (b) More than 30 days: true only if men work faster, which is not given.
  • (c) Less or more: leaves out the equal case (exactly 30 days), so it is not a safe conclusion either.

Quick trick

  • One equation with two unknown rates (man and woman) cannot fix a second combination.

Remember

To compare two mixed groups, you need the ratio of their members' efficiencies.

Hence the answer is (d).

Share
Ask Atlas (4) for similar questions
  1. 2023 · Q30 Time Work Monday Tuesday — Same time-and-work idea: rates of individual workers combined across days, not just the question pattern.
  2. 2024 · Q36 Averages Weight Average Solution — Same question pattern: relating unlike-group quantities through equal totals, leaving answer dependent on given data.
  3. 2020 · Q60 Time Work Complete Together — Compares two workers' individual rates to find combined completion time, like comparing unequal efficiencies.
  4. 2017 · Q54 Time Work Thrice Fast — Uses relative efficiencies of workers to decide sharing; requires comparing individual rates.

← Full UPSC CSE 2022 CSAT paper · All Basic numeracy questions